Apr 29 Update
Apr 29 - work has continued since the last update on the exterior landscaping. This picture shows the freshly laid sod in at the back of the building between the back patio and trees. Work is...
View ArticleMar 22 Update
Mar 22 - the work has continued on the drywall and ceiling grid on the first floor. Much of that work has been completed for the second floor and is now being completed for the first floor. This photo...
View ArticleApr 1 Update
Apr 1 - the floor of the main lobby has been completed. This photo shows the view of that floorig from the second floor overlooking the lobby.
View ArticleApr 30 Update
Apr 30 - work is continuing on the interior finishes. This picture shows the work spaces within the Connectional Ministries office for administrative support.
View ArticleMay 7 Update
May 7 - Much of the furniture that was ordered is now in place. This picture shows the typical furniture chosen for an office. In general, the common area furniture is being purchased new and a little...
View ArticleMay 10 Update
May 10 - the landscaping is essentially complete and the paving in the parking lot has been completed. This picture shows some parking areas leading up towards the southeast side of the building. The...
View ArticleMay 25 Update
May 25 - the Conference Board of Trustees met to tour the new facility on May 25. This photo shows the development consultant briefing the trustees on progress and items left to complete.
View ArticleMay 27 Update
May 27 - progress has continued on the finishing touches for the inside and outside of the facility. This photo shows the singange on the corner of the building with the street number (700). Several...
View ArticleJune 6 Update
The chapel art and communion table is shown in this picture. The dedication of the Dixon Chapel and Meeting Room was held on June 6, 2010.
View ArticleJun 24 Update
Jun 24 - We're moving in! The building is essentially complete though the contractor is still working on a few items on the punch list. Most of the furniture is in and the movers are in the process of...
View ArticleBuilding Exterior
The building exterior will feature brick on the first floor with a textured masonry finish on the second floor.
View ArticleSite Plan
Preliminary plans for the building site will place the building at the back of the lot (closest to Hwy 70) with tree buffers on all sides of the building.
View ArticleMay 8 Update
May 8 - First progress picture showing surveyor's stakes getting ready for driveway clearing.
View ArticleMay 22 Update
May 22 - Tree clearing began this week and part of the driveway is cleared. The driveway will go to the back of the lot so this is the first section that will allow for the small bridge over the wet...
View ArticleGroundbreaking - May 29
The groundbreaking ceremony was held on May 29, 2009. Bishop Al Gwinn participated in the ceremony and directed the ground to be broken. He is shown here turning ground after his call to God to bless...
View ArticleMay 29 Update
May 29 - work continued this week to prepare the driveway for the bridge over the wet part of the lot. The track hoe was digging out the area to prepare for the concrete piping to be laid.
View ArticleGroundbreaking - May 29
As part of the groundbreaking ceremony, ground was broken by Cashar Evans, Bishop Al Gwinn, Melba McCallum, and Christine Dodson in response to directives from Bishop Gwinn on using this land and...
View ArticleJune 5 Update
June 5 - work this week was focused in laying the concrete pipe for the bridge over the wet area of the lot. This picture shows the piping. Dirt covers the piping and creates the base for the bridge...
View ArticleJune 15 Update
Jun 15 - The small bridge is now covered with dirt and can be used to cross the wet area of the lot to get to the rest of the driveway.